Concrete batching
Your current location: 首 页 > Baoding simple mixing plant

Baoding JS1000 mixing plant

2023-03-07 10:25:10
Baoding JS1000 mixing plant
Detailed introduction:

Concrete mixing plant equipment

1.The person in charge of mechanical and electrical equipment should guide, check, urge, and driver to carry out "cross operation" on the equipment before opening every day.。In particular, attention should be paid to the correction of the equipment belt and the cleaning of the metering pressure sensor。

2.In the case of continuous pouring of large volume concrete members。Special process control should be carried out on the equipment and appropriate emergency measures should be formulated。

Concrete mixing plant equipment

(1) Focus on maintenance of parts prone to failure, and ensure that there are appropriate parts reserve;

(2) Contact the power supply department and ask it to provide reliable power guarantee;

(3) Keep the standby generator in good technical condition;

(4) Maintain and prepare sufficient concrete transport vehicles (to be slightly surplus)。The device readiness information can be sent to the dispatcher only when the device is ready。

3.The mixing station should be equipped with two hydraulic pipes, so as to use other power to unload the concrete in the tank when the concrete transport truck fails。Appropriate spare pick, timely removalConcrete mixing transport truckSolidified concrete in the tank。 Equipment maintenance, adjustment, maintenance, cleaning, must be cut off the main power switch, and hang "maintenance, do not close" warning sign。

4.Concrete mixing plantElectronic control equipment, high technical content, should be equipped with experienced electricians, responsible for the daily maintenance of electrical equipment。


Previous post:Mixing plant2023-03-07
Next post:JS1000 mixing plant2023-03-07

Recent visit: